Minor works items - 2.31
- Jump to
- Item details
- Submission procedure
Item details
| Item no. | 2.31 |
|---|---|
| Item class/type | Class II TypeAEG |
| Nature of works | Removal |
| Scope of works | The works involve canopy |
| Location of the canopy | Projecting from the external wall of a building or from the fence wall |
| Projection from the wall | More than 750mm |
| Constructed of concrete | No |
More details: See Item 2.31 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type A, E, G)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work